DEAR VALUED J-SATINE PURCHASERS AND STAKEHOLDERS
6 June 2025, Friday
THANK YOU FOR TAKING THE TIME TO ATTEND THE J.SATINE PURCHASER ENGAGEMENT SESSION.
Thank you to everyone who joined the J.Satine Purchaser Engagement Session on Tuesday, 3 June 2025. We appreciate your time, your questions, and your feedback.
We hope our presentation on the project’s timeline, the independent building checks, and the safety works helped to answer your concerns.
For those who could not attend, we want you to have the same information. You can revisit the recording of the session by making an appointment with our customer service team at [email protected].
You can also find answers to common questions (FAQ) here.
For any other questions or if you wish to share your thoughts with us, please write to us at the following email addresses:
[email protected] or [email protected]
Thank you for your patience and understanding.
Disclaimer: The information provided in this FAQ is intended for general guidance only. Any interpretation, translation, or reliance on this content is strictly at your own risk. We do not accept any kinds of responsibility or liability for any misunderstanding, misinterpretation, or consequences that may arise or occur from the use of this information. For accurate clarification or legal reference, please consult directly with the relevant authorities or professionals.
FREQUENTLY ASKED QUESTIONS [FAQ] DOCUMENT
LATEST UPDATE 6 JUNE 2025
NO | FOCUS AREA | DETAILS |
1. | Chronology of Events | November 2024 On 6 November 2024, an incident was reported by residents near the site. Jayyid Land Sdn Bhd acted immediately to support investigations by Kuala Lumpur City Hall (DBKL), which identified cracks in the shear walls, columns, and floors, mainly from the eighth floor upwards in Block C. Recognising the importance of safety, we fully cooperated with DBKL’s directive and, on 8 November 2024, paused all construction activities as ordered. We also promptly appointed an independent engineer to assess the structure, committed to submitting all required technical reports, and began planning for remedial works in line with expert recommendations. December 2024 – April 2025 We initiated comprehensive soil and structural investigations in late December 2024, demonstrating our commitment to thoroughness and safety. Throughout this period, we submitted detailed interim and final reports to DBKL, clearly outlining the extent of the damage, proposed repair solutions, and enhanced safety measures. As a responsible developer, we maintained open and regular communication with authorities and purchasers, prioritising transparency and the well-being of all stakeholders.
April – May 2025 In April 2025, we completed and submitted a final report prepared by independent consultants. After careful review, DBKL approved for construction to resume on the SOHO block and Blocks A and B on 21 April 2025. Jayyid Land Sdn Bhd continues to work closely with DBKL and independent experts to ensure that Blocks C and D will only proceed with construction after foundation strengthening is completed and independently verified, reflecting the developer’s unwavering commitment to safety and quality. |
2. | Who decided what the independent engineer should investigate, and who covered the costs? |
|
3. | Why was the cause not found earlier? |
|
4. | What happened to the development?
|
|
5. | What is the remedial work being done? | Remedial works are being carried out to the highest industry standards, under the supervision of independent, qualified professionals. The foundation and affected areas are being strengthened to ensure long-term safety, structural integrity, and the continued quality of your home. The remedial works include:
|
6. | How does J.Satine Residences ensure the thorough and lasting resolution of defects, providing assurance against recurrence? |
|
7. | Is the project safe? What assurance do I have that the property will be safe to live in? |
|
8. | Will you share ongoing updates with purchasers?
|
|
9. | When will construction resume and what is the new target completion date, and will there be an Extension of Time (EOT)? |
|
10. | Will the developer bear/reimburse my bank’s progressive interest payment due to the stop work order? |
|
11. | What are my rights if there is a delay in handover? |
|
12. | Will the defects liability period (DLP) be extended? |
|
13. | Which block is affected? |
|
14. | What are the communication channels available for purchasers to stay in touch with the developer regarding their interests? |
|